Bridge Deck Pour & Traffic Switch

  • Tomorrow/Wednesday, July 21st, 6:00 AM-Noon: Concrete Deck Pour for East Half of Bridge
    • East River Street and Alice Street will be CLOSED for this duration to allow concrete trucks in and out of the work zone
  • Friday, July 23rd: Traffic Switch to East Side of Main Street
    • Both lanes of traffic will be shifted on to the new asphalt on the east side of Main Street from Alice St to Harriet St
    • There will be a traffic crossover between the Bridge and Alice Street until the east half of the bridge is complete