Bridge Deck Pour & Traffic Switch: Tomorrow/Wednesday, July 21st, 6:00 AM-Noon: Concrete Deck Pour for East Half of Bridge East River Street and Alice Street will be CLOSED for this duration to allow concrete trucks in and out of the work zone Friday, July 23rd: Traffic Switch to East Side of Main Street Both lanes of traffic will be shifted on to the new asphalt on the east side of Main Street from Alice St to Harriet St There will be a traffic crossover between the Bridge and Alice Street until the east half of the bridge is complete

TEST TW WEATHER

UPDATED 7/15: WIS 23/Main St Paving

UPDATED paving schedule below due to rain:

 

  • Thursday, July 15th: Noon to 7:00 PM– pave from Harriet St intersection down to Ann St
    • Side Streets Closed: Louisa, Cornelia, Catherine, Harriet
    • Side Streets Open: Alice & Ann
  • Friday, July 16th: 6:00 AM to Noon – pave from Casey’s up thru Ann St intersection
  • Side Streets Closed: Alice & Ann
    • Side Streets Open: Louisa & Catherine

If rain prevents paving from occurring tomorrow, the schedule will be pushed to Monday, July 19th.