Clay Street, Driver Street, and E. North Street Update

Since the last project update on September 30th, Temperley Excavating has completed the following:
Construction:
1.    Street:
        a.    Began final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
                i.      Tentatively scheduled for October 19th.
               ii.      Residents will have to move their vehicles prior to paving.
        b.    Began Landscaping on Clay, Driver, and E. North Streets.
 
Anticipated work to be completed for the weeks of October 17th and October 24th, 2022:
1.    Hot Mix Asphalt Paving is tentatively scheduled for October 19th on Clay, Driver, and E. North Streets.
2.    Complete Landscaping on Clay, Driver, and E. North Streets.