WIS 23/Galena St Update 9/27/2022: WIS 23/GALENA STREET: Asphalt paving schedule: lower layer on Thu 9/29 & Fri 9/30; surface layer on Sat 10/1 & Mon 10/3. Next week: lawn restoration, pavement marking, signs, guardrail, core & install manhole castings. If all goes well, the plan is to open the road to traffic at the end of the day Friday, October 7th Then the remaining work will be completed with the west side parking lane closed and flagging operations may be required at times. October/November: finish block walls and concrete steps. Next Spring (likely April/May): finish staining block walls, install railing on walls and concrete steps, and finish restoration. WIS 23/81 INTERSECTION PAVING: Thursday, September 29th: the crew is scheduled to mill matchline joints, likely in the afternoon. Friday, September 30th: the crew is scheduled to pave the entire intersection, likely in the morning. This work will be completed under flagging operations on both days – EXPECT DELAYS!! Crews are planning to keep the intersection open (no flagging) during the morning and afternoon school traffic rush hours if possible.  

TEST TW WEATHER

Clay Street, Driver Street, and E. North Street Update

Temperley Excavating has completed the following:
 
Construction:
1.    Water Main:
       a.    Completed water main tie-ins at Clay Street and Driver Street Intersections.
2.    Street Excavation:
       a.    Completed street grading/preparation for curb & gutter installation.
Anticipated work to be completed for the weeks of September 19th and September 26th, 2022:
1.    Augelli Concrete to be on-site Monday (9/19/22) to install stringline for curb and gutter installation for Clay, Driver, and E. North Streets. 
2.    Complete curb and gutter installation on Tuesday (9/20/22) for Clay, Driver, and E. North Streets
        a.    **All Residents will be required to stay off new curb and gutter for seven (7) days
3.    Complete flatwork (driveways and sidewalks) on Tuesday or Wednesday
4.    Begin final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets
       a.    No date currently set for paving at this time.
5.    Begin Landscaping on Clay, Driver, and E. North Streets.