Week of March 14th: close road, remove trees, start pavement removal. Work from north to south.
March-April: storm sewer trunkline from River St to Center Hill Rd
April-June: water main/services, sanitary sewer and storm sewer laterals
May-July: retaining walls & railing
June-August: roadway grading & rock
July-August: concrete curb & gutter, sidewalk, steps