Bridge Deck Pour & Traffic Switch: Tomorrow/Wednesday, July 21st, 6:00 AM-Noon: Concrete Deck Pour for East Half of Bridge East River Street and Alice Street will be CLOSED for this duration to allow concrete trucks in and out of the work zone Friday, July 23rd: Traffic Switch to East Side of Main Street Both lanes of traffic will be shifted on to the new asphalt on the east side of Main Street from Alice St to Harriet St There will be a traffic crossover between the Bridge and Alice Street until the east half of the bridge is complete

TEST TW WEATHER

Construction update below for the next few weeks

7/2/2021 Construction update below for the next few weeks. 
There will be no work on Monday, July 5th.  Wishing everyone a safe and happy Independence Day!

 

·  Bridge Work:

o    Next week: finish forming the deck

o    Week of 7/12: install rebar for bridge deck

o    Week of 7/19: pour concrete bridge deck

·  Alice Street to Harriet Street:

o    Next week: finish concrete work (sidewalk, median, driveways) and start final roadway base grading

o    Week of 7/12: asphalt paving

o    Week of 7/19: restoration and hopefully shift traffic to the east side of Main Street on the new asphalt pavement by the end of the week

·  Harriet Street to Minerva Street (West Harriet & Washington Streets)

o    Next 3 weeks: continue with removals, pipe installation (water main, sanitary sewer, storm sewer), and start grading the roadway working from north to south