Construction update below for the next few weeks

7/2/2021 Construction update below for the next few weeks. 
There will be no work on Monday, July 5th.  Wishing everyone a safe and happy Independence Day!

 

·  Bridge Work:

o    Next week: finish forming the deck

o    Week of 7/12: install rebar for bridge deck

o    Week of 7/19: pour concrete bridge deck

·  Alice Street to Harriet Street:

o    Next week: finish concrete work (sidewalk, median, driveways) and start final roadway base grading

o    Week of 7/12: asphalt paving

o    Week of 7/19: restoration and hopefully shift traffic to the east side of Main Street on the new asphalt pavement by the end of the week

·  Harriet Street to Minerva Street (West Harriet & Washington Streets)

o    Next 3 weeks: continue with removals, pipe installation (water main, sanitary sewer, storm sewer), and start grading the roadway working from north to south