Next week’s operations (April 19th thru April 23rd):
· River Street intersection south of the bridge:
o Crew will continue installing water main, sanitary sewer, and storm sewer at the intersection
o WIS 23 Flagging 8 am-7 pm all week as necessary – EXPECT DELAYS
o CTH F / West River St will be CLOSED at WIS 23 starting Monday, April 19th thru Friday, May 7th – emergency vehicle access only
o East River St will remain CLOSED thru Friday, May 7th
· Bridge to Louisa St:
o Pipe crew will continue water main installation
o Alice St will remain CLOSED on the east side of Main St – access to Casey’s will remain open on Alice St, just east of the barricades
o Ann St will remain CLOSED on the east side of Main St
o Water service replacements likely to start late in the week for properties on the east side of Main St from the Bridge to Ann St
§ 48-hour notification will be given to property owners for planned water outages
· Louisa Street to Harriet Street:
o Crew may start removing pavement, especially if there is a rain day and they can’t work on water & sewer
· Harriet Street to Minerva Street:
o No work planned next week at this time