Starting today, Thursday, April 15th Ann Street access will be CLOSED on the east side of Main Street
- Crew will begin removing pavement at the Ann St intersection and work their way to Louisa St
- Pipe crew will continue with water main installation from Alice St up to Ann St
- The Cheese Country Trail crossing at Ann St will be detoured 2 blocks north to Cornelia St between Washington St and Wells St
- A temporary asphalt crosswalk will be installed at Alice St for pedestrians to cross Main St thru the work zone