Since the last project update on October 14th, Temperley Excavating has completed the following:
Construction:
- Street:
- Completed final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
- Paving was rescheduled from October 19th to Saturday, October 29th.
- Residents will have to move their vehicles prior to paving.
- Continued landscaping on Clay, Driver, and E. North Streets.
- Completed final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
Anticipated work to be completed for the weeks of October 24th and October 31st:
- Hot Mix asphalt paving is scheduled for Saturday, October 29th on Clay, Driver, and E. North Streets.