Clay Street, Driver Street, and E. North Street Update

Since the last project update on October 14th, Temperley Excavating has completed the following:

Construction:

  1. Street:
    1. Completed final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
      1. Paving was rescheduled from October 19th to Saturday, October 29th.
      2. Residents will have to move their vehicles prior to paving.
    2. Continued landscaping on Clay, Driver, and E. North Streets.

Anticipated work to be completed for the weeks of October 24th and October 31st:

  1. Hot Mix asphalt paving is scheduled for Saturday,  October 29th on Clay, Driver, and E. North Streets.