Clay Street, Driver Street, and E. North Street Update

Since the last project update on September 16th, Temperley Excavating has completed the following:

Construction:

  1. Street:
    1. Completed installation of concrete curb and gutter on Clay, Driver, and E. North Streets.
    2. Completed installation of concrete sidewalks, concrete steps, and concrete driveways.
    3. Began final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
  2. No date is currently set for paving at this time.

Anticipated work to be completed for the weeks of October 3rd and October 10th, 2022:

  1. Continue final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
  2. Begin Landscaping on Clay, Driver, and E. North Streets.

If you have any questions or need further information, please let me know.

Thanks,

Brice Piotrowski- Delta 3 Engineering