Since the last project update on September 16th, Temperley Excavating has completed the following:
Construction:
- Street:
- Completed installation of concrete curb and gutter on Clay, Driver, and E. North Streets.
- Completed installation of concrete sidewalks, concrete steps, and concrete driveways.
- Began final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
- No date is currently set for paving at this time.
Anticipated work to be completed for the weeks of October 3rd and October 10th, 2022:
- Continue final street grading/preparation for installation of hot mix asphalt on Clay, Driver, and E. North Streets.
- Begin Landscaping on Clay, Driver, and E. North Streets.
If you have any questions or need further information, please let me know.
Thanks,
Brice Piotrowski- Delta 3 Engineering